Project Title: Zanjan 100 Beds Hospital & residential buildings
Employer:
Social Security Council of Zanjan
Supervision (Consulting Engineers):
Khane Sazi Iran Co.
Contract Primary Cost ($):
739,000
Start Date:
1993
Finish Date:
1995

Project Title: Headquarters’ Building of Melli Bank of Zanjan
Employer:
Melli Bank of Iran
Supervision (Consulting Engineers):
Technical office of Melli Bank
Contract Primary Cost ($):
3,071,000
Start Date:
1994
Finish Date:
1998

Visit Gallery

Project Title: Completion of Architectural & Installation items of Central Printing press of Melli Bank of Iran
Employer:
Melli Bank of Iran
Supervision (Consulting Engineers):
Technical office of Melli Bank Contract Primary Cost ($): 3,338,000
Start Date:
1995
Finish Date:
1996

Visit Gallery

Project Title: Installation items and Architectural Management of Main Office Of Ministry of Science, Investigation & Technology
Employer:
Ministry of Science, Investigation & Technology
Supervision (Consulting Engineers):
Asar
Contract Primary Cost ($):
4,914,000
Start Date:
2000
Finish Date:
2006

Project Title: Completion of Construction of Student Dormitory of Tabriz Medical Science University
Employer:
Tabriz Medical Science University
Supervision (Consulting Engineers):
Tadbir Bana
Contract Primary Cost ($):
283,000
Start Date:
2001
Finish Date:
2002

Project Title: Niloofar Residential Complex
Employer:
Private Owner
Supervision (Consulting Engineers):
Rad Negar Naghsh
Contract Primary Cost ($):
1,115,000
Start Date:
2003
Finish Date:
2004

 

Project Title: Construction of Tabriz 400- 600 beds educational Hospital
Employer:
Ministry of health & healing & medical training
Supervision (Consulting Engineers):
Group- 4
Contract Primary Cost ($):
2,715,000
Start Date:
1995
Finish Date:
2005

Project Title: Asalouyeh Multipurpose Sport Complex
Employer:
Pars Special Energy Zone Organization
Supervision (Consulting Engineers):
Jodat & Cooperation
Contract Primary Cost ($):
2,250,000
Start Date:
2005
Finish Date:
2006

Project Title: 12- Km GRP Pipeline to 40’000 m3 Water reservoir of Shiraz
Employer:
Regional Water Organization of Shiraz
Supervision (Consulting Engineers):
Iran-ab
Contract Primary Cost ($):
2,908,000
Start Date:
2006
Finish Date:
2007

Project Title: Landscaping of Pardis Sport site of Asalouyeh
Employer:
Special Energy Pars Co.
Supervision (Consulting Engineers):
Rah-Shahr
Contract Primary Cost ($):
1,767,000
Start Date:
2006
Finish Date:
2007

Project Title: Uromieh Track Field Saloon (Martyr Bakeri)
Employer:
Sport Organization
Supervision (Consulting Engineers):
Darya-Khak-Pey
Contract Primary Cost ($):
2,194,000
Start Date:
2005
Finish Date:
2008

 

 

 

Designed by :Simatarh

Copyright 2009 Goupleh Co.